Anhui Tiankang Group supplied a complete cable and cable accessories package for the Laos SAVAN1 Phase 1 Onshore Wind Project, including 35kV power cables, cable terminations, joints, low-voltage cables and shielded control cables for wind farm electrical collection, distribution and control systems.
| Item | Details |
|---|---|
| Project | Laos SAVAN1 Phase 1 Onshore Wind Project |
| Project Type | Onshore Wind Farm (EPC) |
| Country | Laos |
| Project Location | Near Phin District, Savannakhet Province, Laos |
| EPC Contractor | China Energy Engineering Group Guangdong Electric Power Design Institute Co., Ltd. (GEDI) |
| Application | Wind Farm Electrical Collection System, Power Distribution, Control Systems |
| Industry | Renewable Energy / Wind Power / Energy Infrastructure |
| Scope of Supply | 35kV Power Cables, Cable Terminations, Cable Joints, Low-Voltage Cables, Shielded Control Cables, Cable Accessories |
| Supply Value | RMB 15,388,800 (approx. USD 2.1 million) |
| Contract Date | May 2025 |
| Project Status | Under Execution |
| Documentation | Datasheets / Test Reports / MTC / EPC Documentation |
The Laos SAVAN1 Phase 1 Onshore Wind Project is a renewable energy project located near Phin District, Savannakhet Province, Laos. The project forms part of the country's growing wind power infrastructure and requires reliable medium-voltage electrical collection and distribution systems.
China Energy Engineering Group Guangdong Electric Power Design Institute Co., Ltd. (GEDI), an experienced Chinese engineering company serving power and renewable energy projects, is the EPC contractor for the project.
Anhui Tiankang Group was selected as the cable and cable accessories supplier for the project's electrical collection system, providing a comprehensive package of 35kV power cables, cable terminations, joints, low-voltage cables and shielded control cables. The contract value exceeds RMB 15.3 million, with deliveries scheduled from June 2025.
Wind farms require reliable medium-voltage cable systems to collect electricity from individual wind turbines and transmit it to the substation. The 35kV cable system must withstand outdoor and buried installation conditions, including moisture, temperature variations and mechanical stresses.
The project required multiple 35kV cable configurations with conductor cross-sections ranging from 3×120 mm² to 3×400 mm², together with low-voltage power cables and shielded control cables for different applications across the wind farm.
The project required matched cable accessories, including indoor and outdoor terminations, straight-through joints and related installation accessories, to support reliable cable system installation and connection.
The 35kV cables were specified with waterproof construction, including PE/DSTA/PE-W configurations, requiring appropriate cable construction and manufacturing controls for outdoor and buried installation conditions.
Complete technical documentation, including datasheets, test reports, material certificates and quality assurance records, was required to support EPC review and project acceptance.
Cables and accessories were supplied from China to the Laos project site, requiring export packaging, shipping coordination and delivery scheduling aligned with the construction program.
Anhui Tiankang Group supplied a comprehensive cable and cable accessories package for the Laos SAVAN1 wind project.
ZC-YJLHY23-26/35kV-3×120 mm² — 13 km
ZC-YJLHY23-26/35kV-3×185 mm² — 8 km
ZC-YJLHY23-26/35kV-3×240 mm² — 22.1 km
ZC-YJLHY23-26/35kV-3×400 mm² — 9.2 km
ZC-YJY23-26/35-3×300 mm² — 0.6 km
ZC-YJY23-26/35-3×120 mm² — 0.4 km
ZC-YJSY63-26/35-1×500 mm² — 1.2 km
Note: 35kV cables were supplied with XLPE insulation and PE/DSTA/PE-W or project-specified waterproof constructions.
Indoor cold-shrink terminations with copper-aluminum transition terminals where specified, for 3×120, 3×240 and 3×400 mm² cables
Outdoor cold-shrink terminations with silicone rubber dry-type construction for 3×120, 3×185, 3×240 and 3×400 mm² cables
Indoor and outdoor terminations for ZC-YJY63-26/35-1×500 mm² cables
Indoor and outdoor terminations for ZC-YJY23-26/35-3×300 mm² and 3×120 mm² cables
Surge arresters (10kA-51/134) where specified
Outdoor straight-through joints with waterproof protection boxes
Glass-fiber-reinforced protection boxes for outdoor applications
Joint configurations for 3×120, 3×185, 3×240 and 3×400 mm² cables
ZC-YJY-0.6/1kV-1×630 mm² — 680m
ZC-YJY-0.6/1kV-1×300 mm² — 230m
ZC-YJY-0.6/1kV-1×70 mm² — 120m
ZC-YJY22-0.6/1kV-3×150+1×95 mm² — 100m
ZC-YJY-0.6/1kV-4×50 mm² — 45m
ZC-YJY22-0.6/1kV-4×6 to 4×70 mm² — various lengths
ZC-VV22-0.6/1kV-2×2.5 to 4×6 mm² — various lengths
ZC-KYJVP2-22-0.6/1kV-2×2.5 to 19×1.5 mm² — various lengths
Low-voltage cable terminations for indoor and outdoor applications
Selected cable installation accessories
Factory inspection and test reports
Technical datasheets
Material certificates
EPC project documentation
35kV power cables were selected with XLPE insulation and project-specified waterproof and armored constructions for outdoor and buried installation in the wind farm environment. Multiple conductor cross-sections, from 3×120 mm² to 3×400 mm², were supplied to accommodate different electrical collection requirements.
Matched indoor and outdoor cable terminations were supplied using cold-shrink technology for reliable field installation. Copper-aluminum transition terminals were included where specified for the project. Cable joints with waterproof protection boxes were also supplied for cable routing and connection requirements.
Shielded control cables (ZC-KYJVP2-22 series) were supplied for control and instrumentation signal transmission, with different core configurations selected according to the project cable schedule.
Anhui Tiankang Group provided the required technical documentation, including datasheets, factory test reports, material certificates, inspection records and quality assurance documents. The documentation package supported EPC review, project approval and handover requirements.
Cables and accessories were packaged for international transportation with appropriate protection against moisture and mechanical damage. Deliveries were arranged in two scheduled batches in June 2025 to align with the project construction schedule.
✔ Complete Wind Farm Cable Package Capability — 35kV power cables, cable terminations, joints, low-voltage cables and shielded control cables from a single supply source
✔ Medium-Voltage Cable Capability — 35kV cable solutions for wind farm electrical collection systems
✔ Cable Accessories Integration — matched terminations, joints and related accessories for simplified project procurement
✔ EPC Documentation Support — technical documentation and factory quality records for EPC project review and handover
✔ Export Logistics Support — export packaging, shipping coordination and international delivery support
✔ Large-Scale Manufacturing Capability — supporting high-volume cable requirements for renewable energy and industrial projects
What types of cables are required for onshore wind projects?
Onshore wind projects typically require medium-voltage power cables, such as 35kV cables, for electrical collection, low-voltage power cables for auxiliary systems, and shielded control cables for control and instrumentation applications.
Can Tiankang supply complete cable packages for wind farm projects?
Yes. Tiankang can supply cable packages including medium-voltage power cables, low-voltage cables, control cables, cable terminations, joints and related accessories according to project specifications.
Does Tiankang provide cable accessories with cable supply?
Yes. Tiankang can supply matched cable terminations, joints and related installation accessories together with cable products, subject to project requirements.
What cable standards does Tiankang follow?
Tiankang manufactures cable products according to applicable IEC standards, national standards and project-specific specifications, depending on the cable type and application.
Whether you are developing an onshore or offshore wind project, solar power plant or other renewable energy facility, our engineering team can help you prepare a complete cable supply package based on your specifications, cable schedule and project requirements.
We provide complete solutions for:
✔ Onshore and Offshore Wind Farms
✔ Solar Power Plants
✔ Power Transmission and Distribution
✔ Industrial Manufacturing Facilities
✔ Oil & Gas and Petrochemical Plants
✔ Infrastructure and Utility Projects
Contact Our Engineering Team
Yin Shuangjie
International Sales Manager
📧 Email: [email protected]
📱 WhatsApp / Zalo: +86 17856068126
🌐 Website: https://www.tiankang-global.com
This case study is based on project delivery records. For reference purposes only.